F-05 · Project name on warranty differs from requirement documents
Riverside Office HVAC (CS-PILOT-0142) · requirement R-10 · Cross-document consistency
What this means
The warranty certificate names 'Riverside Ofc. Phase II'. Requirement documents name 'Riverside Office HVAC'. This may be an abbreviation or may point to a different project.
Original stored explanation retained; no safe automatic simplification is available.
What would resolve it
Supply evidence addressing the stated requirement: Warranty shall identify the project name and the equipment tags covered.
Your review
Review the sources and the stored routing reasons below, then record your decision. The supplied evidence does not settle this finding automatically. Check: An abbreviated project name may or may not be the same project. A person has to weigh the naming against the rest of the package.
Missing or incomplete supplied evidence does not prove that the work or event never occurred. Readable context alone does not establish absence.
Sample only. Changes are temporary; Reset demo restores the sample. No customer request is submitted.
How this finding was routed
An abbreviated project name may or may not be the same project. A person has to weigh the naming against the rest of the package.
Routed to a person because the cited sources alone do not settle it.
Evidence
Project requirement on the left, supplied source excerpts on the right. Panels stack on small screens.
Project requirement
Warranty shall identify the project name and the equipment tags covered.
Supplied files
Project: Riverside Ofc. Phase II — Equipment: rooftop units (4).
Proposed next action
Confirm the warranty applies to this project, or request a certificate naming the project as identified in the requirements.
Reviewer decision
Use the sample actions to preview each reviewer outcome.